Which 2 actions should the Team Manager take to check that the completed products have been approved as required?


The Team Manager has received notification that the new hardware and software solution has been installed and completed, but there is a concern that it has not been approved by the appropriate people.

Which 2 actions should the Team Manager take to check that the completed products have been approved as required?
A . Check the Work Package to ascertain who should approve the completed Work Package.
B . Check the Product Descriptions to ascertain who should have approved the products.
C . Check the Configuration Management Strategy for product handover procedures.
D . Check the approval records as required in the Work Package.
E . Check the Product Descriptions for the quality method required.

Answer: BD