While producing the Team Plan to deliver the agreed Work Package, it became apparent that the user representatives assigned 10 check some of the products were unsuitable.
Which 2 actions should the Team Manager take in response to this situation?
A . Consult the Senior Supplier to assign suitable reviewers.
B . Discuss the situation with Project Assurance and agree the changes or additions to the reviewers. Advise the Project Manager of this risk.
C . Ensure the Quality Register is updated with details of the agreed amendments to the reviewers.
D . Notify the Project Manager by raising an Exception Report explaining that the original reviewers are unsuitable.
Answer: AB