PdfPrep.com

Which 2 actions should the Team Manager take in response to this situation?

Two weeks after starting work the Team Manager noticed that each completed product had exceeded its estimated effort by around 10%. If this trend continues the Work Package will exceed its agreed cost tolerance of 5%.

Which 2 actions should the Team Manager take in response to this situation?
A . Check the status of the products currently being worked on and analyze the effort expended, to determine if the trend is continuing.
B . Update the Team Plan by increasing all future work estimates by 10%.
C . Amend the Work Package and ensure that the revised targets are met.
D . Escalate the situation in the next Checkpoint Report.
E . Raise an issue that costs will exceed tolerance if the current trend continues.

Answer: AE

Exit mobile version