Posted by: Pdfprep
Post Date: January 7, 2021
Two weeks after starting work the Team Manager noticed that each completed product had exceeded its estimated effort by around 10%. If this trend continues the Work Package will exceed its agreed cost tolerance of 5%.
Which 2 actions should the Team Manager take in response to this situation?
A . Check the status of the products currently being worked on and analyze the effort expended, to determine if the trend is continuing.
B . Update the Team Plan by increasing all future work estimates by 10%.
C . Amend the Work Package and ensure that the revised targets are met.
D . Escalate the situation in the next Checkpoint Report.
E . Raise an issue that costs will exceed tolerance if the current trend continues.
Answer: AE
Leave a Reply