When should Node Replication be scheduled to run?

Posted by: Pdfprep Category: C9060-528 Tags: , ,

When should Node Replication be scheduled to run?
A . when the database backup is running
B . when no restore clients are running
C . when no other Admin processes are running
D . when backup-archive clients are running

Answer: C

Explanation:

Ensure that you are running node replication after client backup.

Complete data deduplication processing before replication processing. Schedule compression after replication.

Figure. Daily schedule when data deduplication and node replication are used

References: https://www.ibm.com/support/knowledgecenter/SSEQVQ_8.1.0/perf/t_srv_sched_deduprep.html