When should application controls be considered within the system-development process?

Posted by: Pdfprep Category: CISA Tags: , ,

When should application controls be considered within the system-development process?
A . After application unit testing
B . After application module testing
C . After applications systems testing
D . As early as possible, even in the development of the project’s functional specifications

Answer: D

Explanation:

Application controls should be considered as early as possible in the system- development process, even in the development of the project’s functional specifications.