When should a full risk assessment and authorization be carried out for a standard change?

When should a full risk assessment and authorization be carried out for a standard change?
A . Each time the standard change is implemented
B . When the procedure for the standard change is created
C . At least once a year
D . When an emergency change is requested

Answer: B