When should a change request be submitted to resolve a problem?
A . As soon as a solution for the problem has been identified
B . As soon as a workaround for the problem has been identified
C . As soon as the analysis of the frequency and impact of incidents justifies the change
D . As soon as the analysis of cost, risks and benefits justifies the change
Answer: D