When reporting risk assessment results to senior management, which of the following is MOST important to include to enable risk-based decision making?
A . A list of assets exposed to the highest risk
B . Potential losses compared to treatment cost
C . Recent audit and self-assessment results
D . Risk action plans and associated owners
Answer: B