When project requirements are documented in user stories then prioritized and refined just prior to construction, which approach is being used for scheduling?

When project requirements are documented in user stories then prioritized and refined just prior to construction, which approach is being used for scheduling?
A . Iterative scheduling with backlog
B . On-demand scheduling
C . Life cycle scheduling with backlog
D . Defining iterative activities

Answer: A