When producing an Exception Plan for a stage, why would the Quality Register be updated?

When producing an Exception Plan for a stage, why would the Quality Register be updated?
A . The Quality Register is NOT updated when creating an Exception Plan
B . To add details of any new quality management activities planned
C . To close all quality checks from the Stage Plan that’s about to be replaced
D . To record any corrective actions required when the quality checks of products in the current Stage Plan were completed

Answer: B