The following settings are defined for a freight order from location A to location B with two freight units:
* The distance between locations A and B in the transportation lane is 1500 km, the duration is 19 hours and the Fix Transportation Duration flag is set. The average speed for the means of transport is defined as 100 km/h and the GIS quality flag is NOT set.
Loading and unloading of each freight unit at locations A and B is defined as 1 hour.
The vehicle resource is available weekdays from 8:00 am to 8:00 pm.
• Loading starts on Monday at 8:30 am.
When is unloading finished? Please choose the correct answer.
A . Tuesday 7:30 pm
B . Tuesday 5:30 pm
C . Tuesday 7:30 am
D . Tuesday 3:30 pm
Answer: A