When is the Risk Management Strategy produced?
A . After authorization has been given to proceed with the initiation stage
B . Before the planning of the initiation stage
C . As soon as the Project Manager has been appointed at start-up
D . After the Project Board have approved the Project Initiation Documentation
Answer: A