When is the earliest that a workaround can be documented in ‘problem management’?

When is the earliest that a workaround can be documented in ‘problem management’?
A . After the problem has been logged
B . After the problem has been prioritized
C . After the problem has been analyzed
D . After the problem has been resolved

Answer: C