When does the project team determine which dependencies are discretionary?

When does the project team determine which dependencies are discretionary?
A . Before the Define Activities process
B . During the Define Activities process
C . Before the Sequence Activities process
D . During the Sequence Activities process

Answer: D

Explanation: