When considering risks, which describes an opportunity in a project?
A . An uncertain event that could have a negative impact on objectives
B . An uncertain event that could have a favourable impact on objectives
C . An event that has occurred resulting in a negative impact on objectives
D . An event that has occurred resulting in a favourable impact on objectives
Answer: B