What’s the purpose of the ‘Plan’ step within the risk management procedure?
A . Create a Risk Management Strategy for inclusion in the Project Initiation Documentation
B . Establish the Project Board’s specific risk management responsibilities and assign them as owners of specific risks
C . To plan the Communications Management Strategy in order to identify and capture any external stakeholder risk information requirements
D . To identify suitable management responses to be implemented to manage a risk, should the risk occur
Answer: D