What would likely happen if management only changed the organization’s current terminology to fit Scrum without the proper understanding and support of Scrum as defined in the Scrum Guide?

Posted by: Pdfprep Category: PSM II Tags: , ,

What would likely happen if management only changed the organization’s current terminology to fit Scrum without the proper understanding and support of Scrum as defined in the Scrum Guide?
A . Very little change will happen as the vocabulary in Scrum is specifically defined for implementing Scrum.
B . The organization may not realize the real benefits of Scrum as there would be no real change on the way the teams work.
C . Organizations may feel less stressed as the behaviors would remain familiar to management.
D . All answers apply.

Answer: D

Explanation:

The defined terminology in Scrum was selected, designed, and defined specifically for supporting the

Scrum Framework. Understanding the differences between traditional methods and the Scrum Framework will help move teams in the right direction in Scrum adoption.