An organization prefers to execute projects using an adaptive approach. However, the new project is much more complex than previously executed projects.
What will the business analyst (BA) recommend?
A . Select an extreme programming approach
B . Review current approach with key stakeholders
C . Follow a predictive approach
D . Choose an agile programming approach
Answer: C
Explanation:
Predictive approach: An approach where planning and baselines are established early in the life cycle of the initiative in order to maximize control and minimize risk.