PdfPrep.com

What type of prioritization approach does Marsha want to use in this scenario?

Bradley is working with the business analyst Marsha to prioritize requirements for their organization. Marsha insists that the requirements be ranked on the cost-benefits analysis of the relative value to the organization.

What type of prioritization approach does Marsha want to use in this scenario?
A . Likelihood of success
B . Business value
C . Urgency
D . CBR Ratio

Answer: B

Explanation:

Marsha wants to utilize the business value of the requirements using a cost-benefit analysis of each requirement. The requirements with the higher value are most important.

Answer. A is incorrect. This is not a valid approach to be used in this scenario.

Answer. D is incorrect. There is not a basis for prioritization called the CBR ratio; this is not a valid choice.

Answer. C is incorrect. Urgency prioritizes requirements based on time sensitivity.

Exit mobile version