What two key components of the project management plan are used as inputs to create the cost management plan?

What two key components of the project management plan are used as inputs to create the cost management plan?
A . Schedule management and risk management plans
B . Schedule management and scope management plans
C . Procurement management and schedule management plans
D . Resource management and schedule management plans

Answer: C