You are the business analyst for a large software development project. There are several issues that must be resolved by certain dates or the problem will prevent the project from advancing.
What technique can you use to track problems with the requirements?
A . Issue tracking
B . RTM
C . Problem tracking
D . Baselining
Answer: C
Explanation:
The technique you’ll use is simply problem tracking. This technique allows the business analyst to manage any issues identified within requirements by stakeholders and to ensure that those issues are resolved. Problem tracking allows the business analyst to manage any issues identified within requirements by stakeholders and to ensure that those issues are resolved. It provides an organized approach to tracking, management, and resolution of defects, issues, problems, and risks throughout business analysis activities. Management of issues is important so that they can be resolved in a timely manner to ensure success.
Answer. D is incorrect. Baselining the requirements does not track problems but creates a standard set of requirements that deliverables may be compared against.
Answer. A is incorrect. Issue tracking is not a valid business analysis term.
Answer. B is incorrect. An RTM is a requirements trace matrix which tracks requirements through the solution, not issues.