During a review session, an agile team presented done requirements to a group of stakeholders. Stakeholder feedback indicated that the done requirements failed to meet the most pressing needs and provide value.
What should the team have done to prevent this?
A . Reprioritized requirements prior to committing to iteration work
B . Ensured that requirements remained stable during the iteration cycle
C . Had stakeholders focus on items created after the product backlog was initially built
D . Worked on features rather than a set of components
Answer: A