What should the team have done to improve retrospective outcomes?

Posted by: Pdfprep Category: PMI-ACP Tags: , ,

A scrum team has conducted regular retrospectives to discuss immediate concerns and the implementation of improvement actions. Despite this, after a few iterations, the same concerns resurface.

What should the team have done to improve retrospective outcomes?
A . Invited subject matter experts (SMEs)
B . Conducted problem detection to determine root causes
C . Measured and reported the outcome of improvement actions to the team
D . Kept track of all current issues in a log, and then reviewed their progress at the end of every iteration

Answer: B

Explanation:

Reference: https://www.scaledagileframework.com/iteration-retrospective/

Comment (1)

  • Ahmed Soliman Reply

    B – Correct

    From PMI’s Agile Practice Guide, Page 51:

    “The retrospective is about looking at the qualitative (people’s feelings) and quantitative (measurements) data, then using that data to find root causes, designing countermeasures, and developing action plans.”

    July 24, 2021 at 2:04 pm