An event management team is following an agile approach to prepare for an upcoming conference. The regional sales manager, from where the conference is to be held, contacts the team with a number of questions about the company’s booth.
What should the team do?
A . Inform the sponsor about the regional sales manager’s disruptiveness and ask that all questions be diverted to the weekly meetings.
B . Stay focused on the current iteration and let the project manager deal with the regional sales manager’s questions.
C . Invite the regional sales manager to the next iteration review to share the progress.
D . Create a risk on the risk register to account for some potentially new requirements from the regional sales manager.
Answer: C