Midway through a sprint, a scrum team member advises the team of a new requirement that may change the initial scope.
What should the team do?
A . Work on requirements that the product owner may have overlooked
B . Record the scope creep in the change management log
C . Add the new requirement to the product backlog
D . Ask the scrum master to secure additional time and resources
Answer: B