A scrum master assumes a project that is essential to organizational growth. The project is expected to be in production for three years.
What should the scrum master do first?
A . Work with the customers to build the product backlog and identify their initial requirements.
B . Meet with the stakeholders and enterprise architects to understand the project’s vision.
C . Plan and execute a sprint 0 to establish the project’s foundational needs.
D . Create a backlog, and execute a sprint 1 to quickly deliver value to the customers.
Answer: C