During a sprint, the team encounters a technical problem that becomes an impediment to completing two stories.

What should the scrum master do?
A . Ask the lead developer to identify a solution, and then share the details with the team
B . Ask a technical manager or architect to determine a solution to the problem
C . Work with the product owner to add a spike to the next sprint to identify a solution
D . Create a collaborative team environment so that the team can explore a solution together

Answer: A