During a current sprint, a team member asks permission from the scrum master to investigate an alternative design approach.
What should the scrum master do?
A . Discourage the team member from deviating from the plan and document the request during the retrospective
B . Encourage the team member to research the issue and present the findings during the retrospective
C . Discourage the team member from using experimentation/spikes unless it is fully developed and accounts for a variety of use cases
D . Encourage the team member to use experimentation/spikes for continuous improvement and help the team understand why it is important
Answer: B