An agile team member from a cross-functional team has been unable to complete assignments due to tasks assigned by the functional manager.
What should the Scrum Master do?
A . Dismiss the team member
B . Discuss the situation with the functional manager
C . Report the functional manager to the project sponsor
D . Demand that the functional manager respects the project charter
Answer: B