The scrum master for a large project must provide an estimate of what can be delivered in six months.
What should the scrum master do?
A . Commit to a specific feature set for delivery
B . Explain that a commitment will be provided after planning
C . Have the team estimate in story points to commit to a specific set of features
D . Use the team’s historical velocity to calculate a range of features that can be delivered
Answer: C