A product owner with experience in a predictive approach wants the team to develop very detailed schedules and cost estimates for the next 10 sprints.
What should the Scrum Master do?
A . Suggest the product owner start by focusing on the next 2 sprints instead of 10
B . Spend the first few sprints to develop detailed schedules and budgets
C . Invite the product owner to the retrospective to explain the team’s approach to schedule and budget
D . Explain that detailed project schedules and budgets are not artifacts in agile projects
Answer: C