A system owner calls the project team to inquire about a recent change in one of the requirements, and insists that the change was never requested.
What should the project team do to investigate the issue?
A . Record a defect for fixing
B . Consult with the project manager
C . Revert back the changes
D . Check the audit history of changes
Answer: D