PdfPrep.com

What should the project leader do?

An agile project has three more iterations before the release. There is a lot of report functionality to be created and defects to be cleared. During a daily scrum, a team member suggests a timebox spike to find a more efficient way to deliver reports.

What should the project leader do?
A . Encourage the team to self-organize and determine how to best complete their existing work and this spike.
B . Encourage the team to complete their just existing work since the team velocity indicates they are already struggling to meet the release goal.
C . Direct the team to defer the spike until the next release and add the action on the backlog for prioritization.
D . Direct the team to work on the spike immediately given the importance of reporting functionality to complete the iteration.

Answer: A

Exit mobile version