After an organization initiates a strategic program, several project managers express interest in joining the program team . The program manager’s supervisor recommends a list of project managers to be part of the team.
What should the program manager do to select the project managers?
A . Complete a skill set inventory and select the most suitable resource(s)
B . Ask interested project managers for their CV or résumé and conduct interviews
C . Accept the recommendation of the program manager’s supervisor
D . Contact the human resource manager for project managers’ availability
Answer: A