The program manager has a global program with five component projects . The program sponsor wants the management plans, processes/procedures, and technology to be uniform across the program . The requirements will create issues and result in increased costs . The program sponsor is new and has imposed these new requirements six months into a three-year program.
What should the program manager do next?
A . Accept what the program sponsor requires and implement the changes.
B . Discuss the proposed changes with the stakeholders and project managers, and give the program sponsor the best option.
C . Respond to the program sponsor if the program sponsor asks about it a second time.
D . Present the risks and benefits of the changes to the program sponsor.
Answer: B,C