To create market advantage, a program sponsor requests accelerating the implementation of a new manufacturing process that is based on a recently improved system component . The program manager is concerned that the delivery of some program goals could be jeopardized.
What should the program manager do?
A . Document the concerns that program goals may be affected and present at the next program governance board review meeting for guidance and actions to be taken
B . Advise the program sponsor that the program will continue and follow the program management plan, unless the change control board (CCB) has approved changes to the plan
C . Work with the project managers of the affected components to implement fast tracking and update the resource management plan accordingly
D . Evaluate critical success factors and key performance indicators (KPIs) to monitor benefits throughout the program’s life cycle
Answer: A