During a backlog refinement meeting, a senior team member raises a concern about an epic sizing that requires the use of a new interface for a vendor product. The product owner acknowledges this as a risk.
What should the product owner do now?
A . Log the risk in the risk register, and share the information with impacted stakeholders at the next monthly review meeting.
B . Create a spike story to determine what needs to be done to use the new interface.
C . Lower the epic’s priority so that it can be deferred, and analyze it during backlog refinement meetings.
D . Move the work to the vendor, since they have better knowledge of interface implementation.
Answer: A