What should the product owner do?

An agile team is working on the first sprint, and have already planned the second and third sprints.

However, market conditions now require a change to the features.

What should the product owner do?
A . Communicate the importance of the business need to the team and refine the product backlog.
B . Ask the team to discuss the changes to the features with the customer.
C . Meet with the agile team lead to prioritize the requirements.
D . Discuss and prioritize the requirements with the team.

Answer: D