A new product owner needs to manage the backlog of a high-visibility, fast-moving project that is consuming a considerable amount of time.
What should the product owner do?
A . Schedule regular meetings with the scrum team to write, groom, and size user stories
B . Focus on stories based on the highest number of story points to first address those items with the highest value
C . Seek regular input from project stakeholders, and reflect this input in the backlog’s priorities
D . Schedule in-person, monthly meetings with key stakeholders to review the project’s progress
Answer: A