In a functional organization, the director of an important stakeholder business group expressed concern to a line manager about the progress of the project.
What should the line manager do next?
A . Hold a face-to-face meeting with the project manager and warn them
B . Point the director to a link where they can take a look at the reports
C . Invite stakeholders to attend monthly progress review meetings
D . Ask the project manager to update the monthly status report distribution list
Answer: C