A business analyst (BA) is working on a project that has a number of stakeholder conflicts and issues. The BA is finding it difficult to resolve the conflicts and issues effectively.
What should the BA do to prevent a similar situation in the future?
A . Plan business analysis governance
B . Verify requirements
C . Perform stakeholder analysis
D . Validate requirements
Answer: C
Explanation:
Stakeholder analysis involves identifying the stakeholders that may be affected by a proposed initiative or that share a common business need. Stakeholder analysis notes, considers, and analyzes the various characteristics of the identified stakeholders.