Posted by: Pdfprep
Post Date: January 7, 2021
Agile team A struggles to deliver committed stories due to technical dependencies with team B, which continuously fails to meet its delivery commitments.
What should the agile team lead do?
A. Create a new team to deliver the dependencies, and bring team B under performance management.
B. Conduct a vision-sharing session with the teams to communicate the project’s overall goals.
C. Swap team members from both teams so that deliveries are better supported.
D. Discuss negotiating the delivery timelines with team A.
Answer: B
Leave a Reply