An agile team delivered a feature in the last iteration. The product owner, who missed the planning and review meetings, was dissatisfied with the feature. The team conducted a retrospective and reviewed the user stories related it.
What should the agile team do next?
A . Ensure that the product owner reviews the acceptance criteria for delivered user stories.
B . Augment the quality assurance and continuous integration processes for delivery.
C . Approach the relevant developers and testers regarding quality issues in upcoming iterations.
D . Ask the product owner to define the entire scope of delivery two to three iterations in advance.
Answer: C