An agile team’s client has been asked to expedite the delivery of the next release. By delivering one month early, the company can generate US$40,000 more than expected for the quarter.
What should the agile team do?
A . Adhere to the new deadline and immediately advise the client that the schedule has been expedited.
B . Advise the client that it is best to continue as planned rather than introduce unforeseen risks by expediting the schedule.
C . Submit a change request to the client with a 50% increase in charges due to the new potential profit.
D . Request additional resources to meet the expedited deadline and obtain training for the new resources.
Answer: A