The project team is ahead of schedule and beginning to gold-plate the feature included in the current sprint.
What should the agile project manager do?
A . Since the team has extra time, notify the product owner and secure approval for the extra work on this feature.
B . Encourage the team to document the improvement and prioritize it for the upcoming iteration, instead of building it now.
C . Instruct the Scrum Master to have the team use the extra time to complete the extra feature work in the current iteration.
D . Notify the product owner and have the product owner verify the backlog priority, then encourage team to continue working on the backlog.
Answer: C