During an iteration planning meeting, the team suggests changes to add product value that will require extra work and impact the schedule.
What should the agile project leader do?
A . Re-estimate the project.
B . Finish the product as it was initially planned.
C . Try to include as many changes as possible.
D . Ask the product owner for approval to proceed.
Answer: A