What should the agile practitioner know about tracking velocity?
A . A team with an average velocity of 50 is twice as efficient as a team with an average velocity of 25.
B . A team with an average velocity of 50 is equally as efficient as a team with an average velocity of 25.
C . A team that consistently meets its planned velocity is more efficient than a team that consistently exceeds its planned velocity.
D . A team that consistently meets its planned velocity is less efficient than a team that constantly exceeds its planned velocity.
Answer: C