PdfPrep.com

What should the agile practitioner do?

Business stakeholders of an agile project frequently skip the review meetings.

What should the agile practitioner do?
A . Ask the product owner to inform all stakeholders about the project’s progress.
B . Send meeting notes to all stakeholders after each review meeting.
C . Include the results of the review meetings in the information radiators.
D . Convince the stakeholders of the benefits of attending the review meetings.

Answer: B

Exit mobile version