A project is starting and the type of work is complex and suitable for agile. In assessing the team members, it appears that co-location would be a challenge.
What should the agile practitioner do?
A . Select and implement collaboration tools to augment team interactions
B . Provide each geographical area with their own product owner and divide the work between the teams
C . Increase the number of requirements documents and ensure they are clearly communicated
D . After several sprints, calculate velocity based on primary team location and use secondary team as reserve
Answer: A